12 men can finish a task in 20 days. How many days will 30 men take to complete the same task?
12 days
8 days
11 days
9 days Question ID : 4410091419936 Option 1 ID : 4410095608661 Option 2 ID : 4410095608658 Option 3 ID : 4410095608660 Option 4 ID : 4410095608659 Status : Answered Chosen Option : B
8 days
Apply the inverse proportion formula directly: D2тАЛ=M2тАЛM1тАЛ├ЧD1тАЛтАЛ=3012├Ч20тАЛ=8 days.
Initial number of men = 12, Initial days = 20, New number of men = 30
M1тАЛ├ЧD1тАЛ=M2тАЛ├ЧD2тАЛ
Apply the inverse proportion formula directly: D2тАЛ=M2тАЛM1тАЛ├ЧD1тАЛтАЛ=3012├Ч20тАЛ=8 days.
Mistakenly treating men and days as directly proportional, leading to incorrect multiplication instead of division.
Identify the Relationship
Since fewer men take more days and more men take fewer days, the number of men and days are inversely proportional. The total work measured in man-days remains constant.
M1тАЛ├ЧD1тАЛ=M2тАЛ├ЧD2тАЛ
Substitute the Values
Substitute the given values into the formula where M1тАЛ=12, D1тАЛ=20, and M2тАЛ=30.
12├Ч20=30├ЧD2тАЛ
Solve for the Unknown
Calculate the total man-days as 240 and divide by 30 to find the required days D2тАЛ.
D2тАЛ=30240тАЛ=8
B is correct because 30 men will complete the same task in 8 days.
This inverse proportionality principle is also extensively applied in problems involving pipes and cisterns as well as speed and time.