6 men finish a job in 8 days. If only 4 men are working, how many days will they take to finish the same job?
10 days
12 days
14 days
8 days
12 days
Use the Inverse Ratio method: The ratio of men is 6:4 (or 3:2), so the ratio of days must be 2:3. Since 2 units = 8 days, 1 unit = 4 days, then 3 units = 12 days.
6 men take 8 days to complete a job, and we need to find the time taken by 4 men.
M1тАЛ├ЧD1тАЛ=M2тАЛ├ЧD2тАЛ
Use the Inverse Ratio method: The ratio of men is 6:4 (or 3:2), so the ratio of days must be 2:3. Since 2 units = 8 days, 1 unit = 4 days, then 3 units = 12 days.
Students often wrongly assume direct proportionality, calculating 64├Ч8тАЛ, which leads to an incorrect result.
Define variables
Let M1тАЛ=6, D1тАЛ=8, and M2тАЛ=4. We need to find D2тАЛ.
M1тАЛ=6,D1тАЛ=8,M2тАЛ=4
Apply Inverse Proportion formula
Since total work is constant, the product of men and days remains the same.
6├Ч8=4├ЧD2тАЛ
Solve for D2
Calculate the value by dividing the total man-days by the new number of men.
D2тАЛ=448тАЛ=12
B is correct because 48 total man-days divided by 4 men results in 12 days.
This concept of inverse variation is fundamental to Pipes and Cisterns and Time and Distance problems where the work or distance remains constant.