A can complete the work in 16 days and B can complete it in 24 days. They work together for 5 days, then A leaves. How many more days will B take to complete the remaining work?
10.5 days
11.5 days
13.5 days
12.5 days
11.5 days
Calculate LCM of 16 and 24 (48 units). A does 3 units/day, B does 2 units/day. In 5 days they do 5×(3+2)=25 units. Remaining 23 units are done by B at 2 units/day in 11.5 days.
A completes work in 16 days, B in 24 days. They work together for 5 days. Find remaining days for B.
Remaining Work=Total Work−(A+B)×Time
Calculate LCM of 16 and 24 (48 units). A does 3 units/day, B does 2 units/day. In 5 days they do 5×(3+2)=25 units. Remaining 23 units are done by B at 2 units/day in 11.5 days.
Students often add A's efficiency back into the division or subtract the wrong remaining amount from the total work.
Calculate Total Work
Find LCM of 16 and 24 to determine total units of work.
LCM(16,24)=48 units
Determine Efficiencies
Calculate units per day for A and B.
EffA=1648=3,EffB=2448=2
Work Done Together
They work together for 5 days at a combined rate.
(3+2)×5=25 units
Remaining Work for B
Calculate remaining work and divide by B's efficiency.
Days=248−25=223=11.5
B is correct because the remaining 23 units of work divided by B's capacity of 2 units/day equals 11.5 days.
This method is directly applicable to pipe and cistern problems, where filling rates replace worker efficiency.