A can do a task in 24 days, while B can do the same task in 16 days. A begins the task and works for 6 days before B joins him. After that, they work together to complete the remaining job. In how many days is the task completed?
15 days
13.2 days
16.2 days
14.5 days Question ID : 441009334021 Option 1 ID : 4410091302030 Option 2 ID : 4410091302029 Option 3 ID : 4410091302031 Option 4 ID : 4410091302032 Status : Answered Chosen Option : B
13.2 days
Practice and solve "A can do a task in 24 days, while B can do the same task in 16 days. A begins the task and works for..." for Mathematics - Previous Year Paper 2026. The correct answer is Option B: 13.2 days. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.
Practice and solve "A can do a task in 24 days, while B can do the same task in 16 days. A begins the task and works for..." for Mathematics - Previous Year Paper 2026. The correct answer is Option B: 13.2 days. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.