A can finish a work in 5 days and B can do the same work in 50 days. B worked alone for 10 days and left the job. In how many days can A alone finish the remaining work? 4045
4
5
5
3
4
Calculate the LCM of time as total work (50 units). A's efficiency is 10/day, B's is 1/day. B does 10 units in 10 days, leaving 40 units for A.
A completes work in 5 days, B completes work in 50 days. B works for 10 days alone then leaves.
Remaining Work=Total Work−WorkDoneB
Calculate the LCM of time as total work (50 units). A's efficiency is 10/day, B's is 1/day. B does 10 units in 10 days, leaving 40 units for A.
Students often subtract B's work from A's efficiency instead of total work, or miscalculate the total remaining work.
Calculate Efficiency
Assuming total work is the LCM of 5 and 50, which is 50 units. Efficiency of A = 50/5=10 units/day. Efficiency of B = 50/50=1 unit/day.
EA=10,EB=1
Calculate B's contribution
B works alone for 10 days at an efficiency of 1 unit/day.
WorkB=10×1=10 units
Determine remaining work
Subtract the work done by B from total units.
Remaining=50−10=40 units
Final calculation for A
A finishes the remaining 40 units at an efficiency of 10 units/day.
DaysA=1040=4
A is correct because A will take 4 days to complete the remaining 40 units of work.
This concept is foundational for Pipe and Cistern problems where efficiency is treated as inflow/outflow rates.