A contractor undertakes a highway project meant to be finished in 50 days, deploying 80 machines. After 30 days, an inspection reveals that only 40% of the work is actually completed. To finish the remaining work perfectly on the original schedule, how many additional machines must he deploy?
120
100
140
80
100
Practice and solve "A contractor undertakes a highway project meant to be finished in 50 days, deploying 80 machines. Af..." for Part 2 Numerical Ability - CILMTIndustrial Engineering 2026. The correct answer is Option B: 100. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.
Practice and solve "A contractor undertakes a highway project meant to be finished in 50 days, deploying 80 machines. Af..." for Part 2 Numerical Ability - CILMTIndustrial Engineering 2026. The correct answer is Option B: 100. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.