A power plant has a maximum demand of 15 MW. Load factor is 50% and the plant factor is 40%. The operating reserve is
MW
75 MW
MW
MW
75 MW
B is correct because the operating reserve is calculated as the difference between the installed capacity (18.75 MW) and the maximum demand (15 MW), resulting in 3.75 MW (Note: The provided option B value of 75 MW in the prompt appears to be a typo for 3.75 MW).
Maximum demand = 15 MW, Load factor = 0.5, Plant factor = 0.4.
Load Factor=Maximum DemandAverage Demand, Plant Factor=Installed CapacityAverage Demand
Calculate Average Demand
Using the load factor formula: Average Demand=LoadFactor×MaximumDemand. Given Load Factor=0.5 and Maximum Demand=15 MW.
Average Demand=0.5×15=7.5 MW
Calculate Installed Capacity
Using the plant factor formula: Installed Capacity=PlantFactorAverageDemand. Given Plant Factor=0.4.
Installed Capacity=0.47.5=18.75 MW
Calculate Operating Reserve
Operating reserve (or Reserve Capacity) is the difference between the installed capacity and the maximum demand.
Reserve=18.75−15=3.75 MW
B is correct because the operating reserve is calculated as the difference between the installed capacity (18.75 MW) and the maximum demand (15 MW), resulting in 3.75 MW (Note: The provided option B value of 75 MW in the prompt appears to be a typo for 3.75 MW).
Always distinguish between Reserve Capacity (difference between installed capacity and maximum demand) and Hot/Cold reserve based on plant status; this is a frequent topic in Power System Economics.