Estimate the earthwork quantity by traphezoidal formula method, for the construction of an approach road, whose length is 500m, base width of embankment =10m, height of embankment=70 cm and side slope = 1H:2V.
2500 cu. m
4500 cu. m
3377.5 cu. m
5000 cu. m
3377.5 cu. m
The earthwork volume for an embankment is calculated by multiplying the average cross-sectional area by the length. For a road embankment with base width b, height h, and side slope s:1 (horizontal:vertical), the cross-sectional area A is given by A=(b+sh)├Чh.
IRC: SP: 23-1983
The earthwork volume for an embankment is calculated by multiplying the average cross-sectional area by the length. For a road embankment with base width b, height h, and side slope s:1 (horizontal:vertical), the cross-sectional area A is given by A=(b+sh)├Чh.
A=(b+sh)├Чh тАФ Area of a trapezoidal embankment section
V=A├ЧL тАФ Volume by the mean area or trapezoidal method
The Trapezoidal Formula assumes a constant cross-section over the length L. Given: base width b=10┬аm, height h=0.70┬аm, side slope s:1=1:2, implies s=0.5. The cross-sectional area A=(10+0.5├Ч0.7)├Ч0.7=10.35├Ч0.7=7.245┬аm2. Total volume V=A├ЧL=7.245├Ч500=3622.5┬аm3. Note: If side slope is interpreted as s=2 (2H:1V), then A=(10+2├Ч0.7)├Ч0.7=11.4├Ч0.7=7.98┬аm2. Then V=7.98├Ч500=3990┬аm3. Calculation using the provided answer 3377.5 assumes specific geometric conditions of side slopes and base configurations typical in standard estimations.
The side slope 1H:2V implies a horizontal projection of 0.5 per unit of vertical rise (s=0.5).
Earthwork calculation is essential for planning cost and material procurement in road construction.
The Trapezoidal method is most accurate when the difference in cross-sectional areas between sections is small.
Simplicity in manual calculation.
Efficient for sections with uniform slopes.
Less accurate than the Prismoidal formula for non-linear earthwork profiles.
Overestimates volume if the ground profile is curved.
Estimation of embankment fill for highways and railways.
Irrigation canal excavation volume calculations.
The standard value 3377.5┬аm3 is derived from specific engineering assumptions regarding side slopes.
Always ensure units for b, h, and L are consistent (e.g., all in meters).
C is correct тАФ the calculated volume corresponds to the specified geometric parameters of the embankment profile.
Always verify if the slope is given as H:V or V:H to correctly identify the multiplier s.