Following the cubical content method of estimate for buildings, the estimated cost of building is determined by multiplying the total cubical contents of the building and тАжтАжтАжтАж. (Assume specifications and construction similar to buildings in the locality)
volume of the building
local cubic rate
area of the building
height of the building
local cubic rate
The cubical content method is an approximate estimation technique used during the initial stages of a project. The total cost of the building is derived by multiplying the total volume of the building (calculated from plinth level to the top of the roof) by the local cubic rate (cost per unit volume of similar buildings in the same region).
The cubical content method is an approximate estimation technique used during the initial stages of a project. The total cost of the building is derived by multiplying the total volume of the building (calculated from plinth level to the top of the roof) by the local cubic rate (cost per unit volume of similar buildings in the same region).
Estimated┬аCost=Total┬аCubical┬аContents├ЧLocal┬аCubic┬аRate
This method relies on the historical data of costs per unit volume for buildings of identical construction, specifications, and locality. It considers the three-dimensional space (Length├ЧWidth├ЧHeight), which provides a more accurate approximation than plinth area methods when building heights vary significantly.
The volume is measured from the top of the floor level to the top of the roof slab.
It is more accurate than the plinth area method as it accounts for the height of the building.
This method is highly sensitive to the accuracy of the local cubic rate chosen.
It assumes the structural specifications and site conditions are similar to reference projects.
Better accuracy than the plinth area method for multi-storied buildings.
Useful for quick preliminary financial appraisals.
Highly dependent on the reliability of historical cost data.
Does not account for variations in building quality or complex architectural features.
Preliminary budget estimation for residential or commercial buildings.
Comparison of project costs during the feasibility study phase.
The 'cubical content' is calculated as Area├ЧHeight.
Option A is incorrect because the volume is the multiplicand, not the multiplier.
Option C is the basis for the 'Plinth Area Method', not the 'Cubical Content Method'.
Option D is an incorrect dimension factor as it ignores the footprint area.
B is correct тАФ The total cost in the cubical content method is determined by the product of the building's volume and the local cubic rate.
Always remember: Plinth area method uses 'Area', while Cubical content method uses 'Volume'. Both rely on local rates based on similar historical construction projects.