Load factor of a power plant is
Generally equal to unity
Always less than unity
Always more than unity
Normally more than unity
Always less than unity
The load factor of a power plant is defined as the ratio of the average load to the maximum demand during a given period. Since the maximum demand is always greater than or equal to the average load over any interval, the load factor is always less than or equal to unity.
The load factor of a power plant is defined as the ratio of the average load to the maximum demand during a given period. Since the maximum demand is always greater than or equal to the average load over any interval, the load factor is always less than or equal to unity.
Load┬аFactor=Maximum┬аDemandAverage┬аLoadтАЛ
Load┬аFactor=Max┬аDemand├ЧTkWh┬аgenerated┬аin┬аT┬аhoursтАЛ
The maximum demand represents the highest power requirement in a specified period, while the average load reflects the total energy consumption divided by the time duration. Because it is physically impossible for the average power drawn to exceed the peak power capacity utilized (as the average is calculated over the entire period including low-demand times), the numerator can never exceed the denominator. Thus, 0тЙдLoad┬аFactorтЙд1.
It measures the utilization efficiency of the power plant capacity.
A higher load factor indicates a more uniform load distribution and better plant economy.
The cost per unit of electricity decreases as the load factor increases.
It is typically expressed as a percentage or a decimal value.
Reduces the cost of generation per unit.
Indicates stable system operation.
Low load factor leads to higher overheads and inefficient fuel usage.
Used by utility companies for tariff structures and system planning.
Basis for calculating fixed charges in power billing.
For most practical power stations, the load factor is always less than 1 because peak demand rarely lasts for the entire duration of the study period.
If the load factor were equal to 1, the demand would be constant throughout the period.
B is correct тАФ The load factor is the ratio of average load to maximum demand, and since average load can never exceed maximum demand, the value is always less than unity.
Always remember that diversity factor is the only common power system factor that is always greater than 1; Load factor, Demand factor, and Capacity factor are always less than or equal to 1.