Point to be consider during site selection of check dam are..
minimum 15000 meter cube water stored by check dam
The river bed should be at least 300 meters above the check dam
both a & b
none of the above
both a & b
Practice and solve "Point to be consider during site selection of check dam are....." for Civil - Water Resources Management. The correct answer is Option C: both a & b. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.
Option **(c) **