Sharad can complete a piece of work alone in 20 days and Varad can complete the same work alone in 60 days. They start the work together, but Sharad leaves 16 days before the work is completed. In how many total days will the work be completed?
26
25
27
28
27
Practice and solve "Sharad can complete a piece of work alone in 20 days and Varad can complete the same work alone in 6..." for Quantitative Aptitude - CCIJunior Assistant Accounts 01 Sep 2026 Shift 1. The correct answer is Option C: 27. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.
Practice and solve "Sharad can complete a piece of work alone in 20 days and Varad can complete the same work alone in 6..." for Quantitative Aptitude - CCIJunior Assistant Accounts 01 Sep 2026 Shift 1. The correct answer is Option C: 27. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.