The most appropriate operating speeds in rpm of generators used in Thermal, Nuclear and Hydro power plants would respectively be
3000, 300 and 1500
3000, 3000 and 300
1500, 1500 and 3000
1000, 900 and 750
3000, 3000 and 300
Generators in thermal and nuclear power plants are typically high-speed turbogenerators (2-pole) operating at 3000 rpm for 50 Hz systems. In contrast, hydro power plants use low-speed salient-pole generators with many poles, often resulting in speeds such as 300 rpm, due to the low head and high torque requirements of water turbines.
Generators in thermal and nuclear power plants are typically high-speed turbogenerators (2-pole) operating at 3000 rpm for 50 Hz systems. In contrast, hydro power plants use low-speed salient-pole generators with many poles, often resulting in speeds such as 300 rpm, due to the low head and high torque requirements of water turbines.
NsтАЛ=P120fтАЛ тАФ relationship between synchronous speed, frequency, and pole count
The synchronous speed NsтАЛ is determined by the relationship NsтАЛ=P120fтАЛ. Thermal/Nuclear plants use steam turbines which are highly efficient at high speeds, necessitating a small number of poles (P=2, NsтАЛ=3000 rpm). Hydro turbines (like Kaplan or Francis) operate at lower speeds requiring high pole counts (e.g., P=20, NsтАЛ=300 rpm) to generate 50 Hz power effectively.
Turbogenerators (Thermal/Nuclear) are cylindrical rotor machines designed for high-speed operation.
Hydro generators are salient-pole machines designed for low-speed operation with high pole counts.
The frequency f is strictly maintained at 50 Hz in India by the grid.
High-speed operation (3000 rpm) reduces the physical size and cost of turbogenerators.
Low-speed operation (300 rpm) in hydro plants handles high hydraulic torque efficiently.
High-speed units require complex cooling systems due to centrifugal stresses.
Large number of poles in hydro generators increases physical size and mechanical complexity.
Thermal/Nuclear: Steam turbine-driven base load power plants.
Hydro: Water turbine-driven peaking or base load power plants.
| Feature | High Speed | Low Speed |
|---|---|---|
Generation Type | Thermal/Nuclear | Hydro |
Thermal and Nuclear power plants use steam turbines (Rankine cycle), which are optimized for high peripheral speeds.
Hydro plants use water turbines (Francis, Kaplan, Pelton), which operate at lower speeds depending on the head.
B is correct тАФ Thermal and nuclear plants use 2-pole high-speed generators (3000 rpm), whereas hydro plants use multi-pole low-speed generators (typically 300 rpm).
Always verify pole count calculations: P=NsтАЛ120fтАЛ. A 3000 rpm generator must have 2 poles for 50 Hz, which is typical for steam-driven units.