Thirty workers can complete a piece of work in 27 days. After working for 6 days, 15 more workers joined them. In how many more days will the work be completed?
14
20
16
15
14
Practice and solve "Thirty workers can complete a piece of work in 27 days. After working for 6 days, 15 more workers jo..." for Part 2 Numerical Ability - CIL MT Civil 2026. The correct answer is Option A: 14. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.