Three workers A, B, C can finish a job in 10, 15, and 20 hours respectively. A and B start; after 2 hours, C joins and they finish the remaining work in t more hours. What is the value of t? (Rounded off to the nearest integer.)
4
5
6
3
3
Calculate total work as LCM(10, 15, 20) = 60 units. A's efficiency = 6, B's = 4, C's = 3. In 2 hours, A+B do 20 units. Remaining 40 units shared by (6+4+3)=13 units/hr, t = 40/13 ≈ 3.07.
Workers A, B, and C finish a job in 10, 15, and 20 hours. A and B work for 2 hours, then C joins for t more hours.
Work=Efficiency×Time
Calculate total work as LCM(10, 15, 20) = 60 units. A's efficiency = 6, B's = 4, C's = 3. In 2 hours, A+B do 20 units. Remaining 40 units shared by (6+4+3)=13 units/hr, t = 40/13 ≈ 3.07.
Students often miscalculate the total remaining work or add C's efficiency before the 2-hour window ends, leading to incorrect time allocations.
Calculate Efficiencies
Assuming total work is the LCM of 10, 15, 20 which is 60 units. Efficiencies are A=6,B=4,C=3.
EA=6,EB=4,EC=3
Initial Work
A and B work for 2 hours, completing 2×(6+4)=20 units.
Wdone=20
Solve for t
Remaining work is 60−20=40 units. All three work at 6+4+3=13 units/hr. Thus t=40/13≈3.07.
t=1340≈3
D is correct because the remaining 40 units divided by the combined efficiency of 13 units/hr yields approximately 3.07, which rounds to 3.
This logic is identical to pipe and cistern problems, where filling rates replace worker efficiencies.