Two alternatives for a construction project are being considered. Both projects have a 5-year life. Alternative A initially costs is Rs. 2,260 and yields Rs. 355 annually for 5 years. Alternative B initially costs Rs. 5,500 and yields Rs. 1,250 annually for 5 years. The rate of return on the difference between the alternatives is approximately
3.60%
8%
12%
15%