Which method of power transmission has more initial cost?
Through overhead line
Through under ground cable
Both have same initial cost
None of above
Through under ground cable
Practice and solve "Which method of power transmission has more initial cost?..." for Electrical - Power System. The correct answer is Option B: Through under ground cable. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.