Examoogle
ExamsTest SeriesCBATRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
🛒0
अA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
© 2026 Examoogle. India's #1 competitive exam AI tutor.
🔒 SSL Secured📱 UPI Accepted🧾 GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
Subtotal₹0
Total₹0
Examoogle • User • info@examoogle.com • EE-2024-8821
Chapter 1 of 12 • Page 1 of 248🔒 Protected PDF • Watermarked
Back to Practice Questions
ElectricalPower System
PrevNext

Which of the following is closed first for supplying power after repair or maintenance?

A

Isolator

B

Earth switch

C

Circuit breaker

D

Relay

Correct Answer

⚙️ TE • Technical Concept & PrincipleElectricalPower System
Option A

Isolator

Quick Summary:

In a power substation, the isolator is a mechanical switching device used for isolation, not for breaking load currents. When restoring power after maintenance, the isolator is closed first to establish a physical connection path before the circuit breaker is operated to energize the circuit.

⚙️TETechnical SolutionConcept & Principle
💡 Explanation

In a power substation, the isolator is a mechanical switching device used for isolation, not for breaking load currents. When restoring power after maintenance, the isolator is closed first to establish a physical connection path before the circuit breaker is operated to energize the circuit.

🔢 Key Formulas

Iload=VZI_{load} = \frac{V}{Z}Iload​=ZV​ — Circuit current magnitude

Parc=Varc×IarcP_{arc} = V_{arc} \times I_{arc}Parc​=Varc​×Iarc​ — Power dissipated in arc during switching

⚙️ Working Principle

The switching sequence in a substation is governed by safety interlocks. When energizing, the isolators are closed first because they are 'off-load' devices, meaning they cannot interrupt the arc. Once the isolator blades are locked in place, the circuit breaker is closed to allow current to flow safely, as the breaker is designed to quench the arc produced during closing or opening under load.

📌 Key Points
  • ▸

    Isolators are 'off-load' devices and must not be operated under current.

  • ▸

    Circuit breakers are 'on-load' devices designed to handle arcs during switching.

  • ▸

    The golden rule of switching: Isolators Close First (ICF) and Open Last (IOL).

  • ▸

    Earth switches must be opened before the isolator is closed to prevent short circuits.

✅ Advantages
  • ▸

    Ensures safety by preventing arc formation at the isolator contacts.

  • ▸

    Isolator provides visual confirmation of disconnection for maintenance personnel.

❌ Disadvantages / Limitations
  • ▸

    Manual or motorized operation of isolators is slower than circuit breakers.

  • ▸

    Cannot clear faults; they rely on upstream breakers.

🛠️ Applications / Uses
  • ▸

    Substation busbar selection.

  • ▸

    Isolating equipment like transformers or lines for inspection.

🔄 Comparison Table
FeatureIsolatorCircuit Breaker

Operation

Off-load (No current)

On-load (With current)

📄 Additional Information
  • ▸

    The isolator acts as a visible air-gap break to ensure complete isolation from high-voltage supply.

  • ▸

    Operating an isolator under load can lead to catastrophic arcing and damage to the substation structure.

📊 Diagram / Illustration
Isolator (CloseFirst)Circuit Breaker(Close Second)Closing Sequence
✅

A is correct — The isolator is closed first during the power supply restoration process as it is an off-load device that establishes the electrical path prior to the circuit breaker being switched.

Core Concepts Used
Click any tag to open in AI Tutor
Substation Switching Sequence On-load vs Off-load switching Arc Quenching
💡 EXAM TIP

Remember the mnemonic 'ICF' (Isolator Close First) for restoration and 'IBL' (Isolator Break Last) for maintenance.

Related Questions

ElectricalPower System
The specified quantities of Generation bus is
ElectricalPower System
When an alternator connected to the bus-bar is shut down the bus-bar voltage will
ElectricalPower System
The current drawn by the line due to corona losses is _______
ElectricalPower System
The specified quantities of load bus are
ElectricalPower System
The advantages of high transmission voltage are ______

Discussion (0)

Loading discussion...
PrevNext