Join 60,000+ competitive exam aspirants
Which of the following is not a type test of CB?
Temprature rise test
Short Circuit making/breaking test
rated short-time withstand the test
Mechanical operation test
Mechanical operation test
Mechanical operation test is NOT a type test; it is classified as a Routine Test (or routine/type test sequence depending on mechanical endurance cycles, but routinely performed on every CB without destructiveness). Type tests on circuit breakers are performed on a prototype to prove design capabilities, which include Temperature Rise, Short-Circuit Making/Breaking, and Short-Time Withstand tests.
IEC 62271-100 / IS 13118:1991 Cl. 6 (Type Tests)
Mechanical operation test is NOT a type test; it is classified as a Routine Test (or routine/type test sequence depending on mechanical endurance cycles, but routinely performed on every CB without destructiveness). Type tests on circuit breakers are performed on a prototype to prove design capabilities, which include Temperature Rise, Short-Circuit Making/Breaking, and Short-Time Withstand tests.
ImakingтАЛ=2.55├ЧIbreaking,rmsтАЛ тАФ Relationship between peak making current and RMS symmetrical breaking current
PheatтАЛ=I2R тАФ Power dissipation evaluated during Temperature Rise Test
Type tests verify the design ratings of a switchgear assembly under extreme stress conditions, such as thermal limits from full load current and electromagnetic forces from short-circuit faults. Routine tests, like basic mechanical operation, verify the proper manufacturing and assembly of every individual unit before dispatch.
Type Tests are conducted on a single prototype representative breaker to confirm compliance with rated standards.
Routine Tests are performed on every manufactured circuit breaker prior to delivery.
Short-circuit making and breaking capacity tests prove the breaker's ability to safely interrupt fault currents.
Mechanical Operation Test checks opening/closing operations at specified control supply voltage limits without load.
Type testing ensures full design integrity and electrical safety limits before mass production.
Routine testing eliminates manufacturing defects on individual production units.
Type testing is destructive and highly expensive due to required high-power laboratory facilities.
Routine testing is restricted to non-destructive electrical and mechanical operations.
Testing high-voltage transmission circuit breakers (SF6, Vacuum, Air Blast).
Certification of switchgear assemblies under IEC 62271 standards.
| Feature | Type Test | Routine Test |
|---|---|---|
Primary Objective | Validate design parameters & limits | Detect manufacturing/assembly flaws |
Applicability | Prototype or sample unit | Every manufactured unit |
Examples | Temp Rise, Short-circuit, Impulse | Mechanical operation, Resistance check |
Option A: Temperature rise test is a Type Test conducted at rated current until temperature stabilizes.
Option B: Short Circuit making/breaking test is a Type Test performed in high-power test labs.
Option C: Rated short-time withstand current test is a Type Test to ensure thermal and dynamic stress withstand capability for 1┬аs or 3┬аs.
D is correct тАФ Mechanical operation test is classified as a routine test performed on every manufactured unit to ensure proper mechanical function.
Remember: High-power tests involving actual fault currents or temperature limits under rated load are ALWAYS Type Tests, whereas functional checks are Routine Tests.