44 men can do a piece of work in 48 days. The number of men required to complete the same work in 8 days is:
260
264
266
261
264
Practice and solve "44 men can do a piece of work in 48 days. The number of men required to complete the same work in 8 ..." for Mathematics - Previous Year Paper 2024. The correct answer is Option B: 264. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.