A and B can complete a piece of work in 8 days and 12 days, respectively. A starts working on the task and after 3 days, B joins him. How many more days will it take to finish the work after B joins?
5 days
2 days
3 days
4 days
3 days
Practice and solve "A and B can complete a piece of work in 8 days and 12 days, respectively. A starts working on the ta..." for Mathematics - Previous Year Paper 2024. The correct answer is Option C: 3 days. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.