A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve is
MW
75 MW
MW
MW
75 MW
B is correct because the calculated operating reserve based on the provided plant and load factors results in 3.75 MW (Note: The provided option 75 MW in the source appears to be a typo for 3.75 MW based on standard electrical engineering definitions).
Maximum demand PmaxтАЛ = 15 MW, Load factor = 0.5, Plant factor = 0.4.
PavgтАЛ=Load┬аfactor├ЧPmaxтАЛPcapacityтАЛ=Plant┬аfactorPavgтАЛтАЛR=PcapacityтАЛтИТPmaxтАЛ
Calculate Average Load
Average load (PavgтАЛ) is found by multiplying the load factor by the maximum demand (PmaxтАЛ):
PavgтАЛ=0.5├Ч15=7.5┬аMW
Calculate Plant Capacity
The plant capacity (PcapacityтАЛ) is derived from the plant factor definition (PavgтАЛ/PcapacityтАЛ):
PcapacityтАЛ=0.4PavgтАЛтАЛ=0.47.5тАЛ=18.75┬аMW
Determine Operating Reserve
The operating reserve (R) is the difference between the installed capacity and the maximum demand:
R=18.75тИТ15=3.75┬аMW
B is correct because the calculated operating reserve based on the provided plant and load factors results in 3.75 MW (Note: The provided option 75 MW in the source appears to be a typo for 3.75 MW based on standard electrical engineering definitions).
In power systems, always distinguish between 'Load Factor' (based on max demand) and 'Plant Factor' (based on rated capacity) to avoid calculation errors in reserve margin.