A region has a maximum demand of 500 MW at a load factor of 50%. The load duration curve can be assumed to be a triangular.Utility has to meet this load by setting up a generating system which has partly hydro and partly thermal. The costs are as under.
Hydro plant: Rs.600 per kW per annum plus 3p per kWhThermal plant: Rs.300 per kW per annum plus 13p per kWh
The energy generated annually by hydro and thermal power plant for minimum cost are
1935├Ч106┬аkWh and 255├Ч106┬аkWh
255├Ч106┬аkWh and 1935├Ч106┬аkWh
187.5├Ч106┬аkWh and 2002.5├Ч106┬аkWh
2002.5├Ч106┬аkWh and 187.5├Ч106┬аkWh
1935├Ч106┬аkWh and 255├Ч106┬аkWh
To achieve minimum cost, the base load should be supplied by the plant with higher capital cost and lower running cost (Hydro), while peak load is supplied by the plant with lower capital cost and higher running cost (Thermal). The intersection point of the two generation costs determines the load division, where the marginal cost of both plants is equal.
To achieve minimum cost, the base load should be supplied by the plant with higher capital cost and lower running cost (Hydro), while peak load is supplied by the plant with lower capital cost and higher running cost (Thermal). The intersection point of the two generation costs determines the load division, where the marginal cost of both plants is equal.
CtotalтАЛ=(PhтАЛ├ЧCf,hтАЛ+EhтАЛ├ЧCv,hтАЛ)+(PtтАЛ├ЧCf,tтАЛ+EtтАЛ├ЧCv,tтАЛ)
Intersection┬аLoad┬аPdтАЛ=8760(Cv,hтАЛтИТCv,tтАЛ)Cf,tтАЛтИТCf,hтАЛтАЛ┬а(for┬аoptimization)
The total annual cost is given by C=Fixed┬аCost+Variable┬аCost├ЧAnnual┬аEnergy. By equating the cost of generation for both plants at the intersection load point, we determine the capacity threshold (PdтАЛ). The Hydro plant handles the base load up to PdтАЛ, and the Thermal plant handles the peak load from PdтАЛ to the maximum demand, calculated using the load duration curve area.
Load Duration Curve (LDC) is triangular: P(t)=PmaxтАЛ(1тИТTtтАЛ)
Hydro plants generally have high initial capital costs but very low operating fuel costs.
Thermal plants have lower initial investment but high operating costs due to fuel consumption.
Total annual hours = 8760 hours.
Optimizes capital expenditure vs operating expenditure.
Increases grid reliability by diversifying energy sources.
Limited by site availability for hydro projects.
Complexity in scheduling and peak load management.
Grid integration of multi-source power systems.
Utility economic dispatch planning.
| Feature | Hydro Capital | Thermal Capital |
|---|---|---|
Cost Component | Rs. 600/kW | Rs. 300/kW |
Fuel Cost | 0.03 Rs/kWh | 0.13 Rs/kWh |
The triangular LDC means average load is half of peak load.
For this problem, the optimal division load is calculated to be 300 MW.
A is correct тАФ The minimum annual cost is achieved when the Hydro plant supplies 1935├Ч10тБ╢ kWh and the Thermal plant supplies 255├Ч10тБ╢ kWh.
In engineering economics problems, always check the units (kW vs MW, p vs Rs) carefully before calculation to avoid magnitude errors.