Join 60,000+ competitive exam aspirants
An industrial consumer has a load pattern of 2000 kW, 0.8 lag for 12 hours and 1000 kW unity power factor for 12 hours. The load factor is
75
75
B is correct because the ratio of the average load (1500 kW) to the maximum demand (2000 kW) over the 24-hour cycle results in a load factor of 75%.
Load 1: 2000 kW for 12 hours. Load 2: 1000 kW for 12 hours.
Load Factor=MaximumDemandAverageLoad=MaximumDemand×TTotalEnergyconsumedintimeT
Calculate Total Energy Consumed
Total energy is the sum of energy in both periods: E=(P1×t1)+(P2×t2)=(2000×12)+(1000×12).
E=24000+12000=36000 kWh
Find Maximum Demand
The maximum demand is the highest power rating observed in the given load pattern, which is 2000 kW.
Pmax=2000 kW
Calculate Average Load
The average load over the total time period (24 hours) is calculated as total energy divided by total time.
Pavg=2436000=1500 kW
Calculate Load Factor
Load Factor is the ratio of average load to maximum demand: LF=20001500.
LF=0.75 or 75%
B is correct because the ratio of the average load (1500 kW) to the maximum demand (2000 kW) over the 24-hour cycle results in a load factor of 75%.
In power systems, the load factor is always less than 1. A higher load factor indicates a more stable and efficient utilization of generating equipment.