Join 60,000+ competitive exam aspirants
The annual load duration curve of power supply system may be considered as a straight line from 40 MW to 8 MW. The load factor of the system is
20%
40%
60%
83.33%
60%
C is correct because the average load is 24 MW, which results in a load factor of 60% when divided by the maximum load of 40 MW.
Maximum Load (Pmax) = 40 MW, Minimum Load (Pmin) = 8 MW. Load duration curve is a straight line.
Load Factor=Maximum LoadAverage Load=Pmax2Pmax+Pmin
Calculate Average Load
Since the load duration curve is a straight line, the average load is the arithmetic mean of the maximum and minimum loads.
Average Load=240+8=248=24 MW
Apply Load Factor Formula
The load factor is defined as the ratio of the average load to the maximum demand over a period.
Load Factor=Maximum LoadAverage Load=4024
Calculate Percentage
Simplify the fraction and convert to percentage.
Load Factor=0.6=60%
C is correct because the average load is 24 MW, which results in a load factor of 60% when divided by the maximum load of 40 MW.
In power systems, the load factor is always less than 1. A higher load factor indicates more efficient utilization of the generating equipment, which is critical for minimizing the cost per unit of electricity generated.