Examoogle
ExamsTest SeriesCBATRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
ЁЯЫТ0
рдЕA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
┬й 2026 Examoogle. India's #1 competitive exam AI tutor.
ЁЯФТ SSL SecuredЁЯУ▒ UPI AcceptedЁЯз╛ GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
SubtotalтВ╣0
TotalтВ╣0
Examoogle тАв User тАв info@examoogle.com тАв EE-2024-8821
Chapter 1 of 12 тАв Page 1 of 248ЁЯФТ Protected PDF тАв Watermarked
Back to Practice Questions
ElectricalPower System
PrevNext

Disadvantage┬а of interconnected power system is

A

Expensive tie line

B

Economical operation

C

Increase the reliability of power system

D

All of the above

Correct Answer

тЪЩя╕П TE тАв Technical Concept & PrincipleElectricalPower System
Option A

Expensive tie line

Quick Summary:

An interconnected power system involves linking multiple generating stations through high-voltage tie lines to share loads and reserves. While this improves efficiency, the requirement for high-capacity tie lines to handle inter-area power flow constitutes a significant economic and technical disadvantage due to high capital expenditure.

тЪЩя╕ПTETechnical SolutionConcept & Principle
ЁЯТб Explanation

An interconnected power system involves linking multiple generating stations through high-voltage tie lines to share loads and reserves. While this improves efficiency, the requirement for high-capacity tie lines to handle inter-area power flow constitutes a significant economic and technical disadvantage due to high capital expenditure.

ЁЯФв Key Formulas

P=V1V2XsinтБб(╬┤)P = \frac{V_1 V_2}{X} \sin(\delta)P=XV1тАЛV2тАЛтАЛsin(╬┤) тАФ Power transfer equation between two areas

╬ФP=PgenтИТPload\Delta P = P_{gen} - P_{load}╬ФP=PgenтАЛтИТPloadтАЛ тАФ Power balance required for frequency stability

тЪЩя╕П Working Principle

The interconnection mechanism relies on synchronizing multiple generators to a common frequency (f=50┬аHzf = 50\text{ Hz}f=50┬аHz in India). Power flows between regions are governed by the phase angle difference ╬┤\delta╬┤ and line reactance XXX, defined by P=V1V2XsinтБб(╬┤)P = \frac{V_1 V_2}{X} \sin(\delta)P=XV1тАЛV2тАЛтАЛsin(╬┤). Installing robust tie lines necessitates expensive switchgear, protection schemes, and high-voltage transmission infrastructure to maintain system stability during transients.

ЁЯУМ Key Points
  • тЦ╕

    Interconnection allows 'Load Diversity' which reduces the required installed capacity.

  • тЦ╕

    Tie lines must be designed for worst-case contingency scenarios, increasing costs.

  • тЦ╕

    System frequency stability is enhanced by the large rotating inertia of the interconnected grid.

тЬЕ Advantages
  • тЦ╕

    Improved reliability through shared spinning reserves.

  • тЦ╕

    Higher economy due to load economic dispatch.

  • тЦ╕

    Reduction in total required installed capacity (Reserve sharing).

тЭМ Disadvantages / Limitations
  • тЦ╕

    Extremely expensive construction and maintenance of tie lines.

  • тЦ╕

    Increased complexity in fault detection and protection coordination.

  • тЦ╕

    Risk of cascading outages across the entire grid during major disturbances.

ЁЯЫая╕П Applications / Uses
  • тЦ╕

    National Grid (e.g., POSOCO/NLDC operations)

  • тЦ╕

    Regional Load Despatch Centres (RLDC)

  • тЦ╕

    Cross-border power trade (e.g., India-Bhutan-Nepal connections)

ЁЯУД Additional Information
  • тЦ╕

    Option B (Economical operation) is actually an advantage, as it enables optimal unit commitment.

  • тЦ╕

    Option C (Reliability) is a primary advantage of the interconnection.

  • тЦ╕

    The cost of tie lines includes not just the physical transmission line, but also the control systems (SCADA) and relaying equipment.

ЁЯУК Diagram / Illustration
Interconnected System ArchitectureArea 1Area 2Tie LineHigh Capital Cost
тЬЕ

A is correct тАФ The high capital investment required for robust tie lines to connect independent systems is a major economic drawback.

Core Concepts Used
Click any tag to open in AI Tutor
Power System Stability Economic Load Dispatch Transmission Infrastructure Economics
ЁЯТб EXAM TIP

Always distinguish between economic 'operation' (a benefit of sharing load) and economic 'investment' (the cost of building tie lines).

Related Questions

ElectricalPower System
The specified quantities of Generation bus is
ElectricalPower System
When an alternator connected to the bus-bar is shut down the bus-bar voltage will
ElectricalPower System
The current drawn by the line due to corona losses is _______
ElectricalPower System
The specified quantities of load bus are
ElectricalPower System
The advantages of high transmission voltage are ______

Discussion (0)

Loading discussion...
PrevNext