For construction of WBM roads, which of the following is the correct sequence of operation after spreading the crushed aggregate?
Filling voids with screening, application of binding material, dry rolling, wet rolling
Wet rolling, application of binding material, dry rolling, filling voids with screening
Dry rolling, wet rolling, application of binding material, filling voids with screening
Dry rolling, filling voids with screening, wet rolling, application of binding material
Dry rolling, filling voids with screening, wet rolling, application of binding material
The construction of a Water Bound Macadam (WBM) road involves a systematic sequence to ensure structural interlocking and density. After spreading the crushed coarse aggregate, the material must be dry-rolled to achieve initial mechanical interlocking, followed by the application of screenings to fill voids, wet-rolling to create a slurry that binds the stones, and finally, the application of binding material (if required) to seal the surface.
IRC: 19-2005
The construction of a Water Bound Macadam (WBM) road involves a systematic sequence to ensure structural interlocking and density. After spreading the crushed coarse aggregate, the material must be dry-rolled to achieve initial mechanical interlocking, followed by the application of screenings to fill voids, wet-rolling to create a slurry that binds the stones, and finally, the application of binding material (if required) to seal the surface.
Void┬аRatio=VtтАЛVvтАЛтАЛ тАФ representing the ratio of volume of voids to total volume
Degree┬аof┬аCompaction=╬│maxтАЛ╬│dтАЛтАЛ тАФ efficiency of rolling operation
Dry rolling provides the initial stability through friction between aggregate faces. Filling voids with screenings ensures a dense graded structure. Subsequent wet rolling allows the fine particles and water to form a mortar-like paste that fills remaining internal voids, resulting in a compacted, rigid road base.
Dry rolling starts from edges and proceeds towards the center.
Screenings are applied in three or more thin layers to ensure uniform filling.
Wet rolling involves heavy rolling while simultaneously sprinkling water to form a grout.
Binding material consists of stone dust or similar material to reduce permeability.
Utilizes locally available materials.
Economical for low traffic volume roads.
Provides good base for bituminous surfacing.
High maintenance requirement.
Poor resistance to heavy rainfall or water logging.
Susceptible to dust generation under traffic.
Sub-base or base course for highways.
Rural or village roads.
The sequence of rolling is critical: Dry rolling тЖТ Screenings тЖТ Wet rolling тЖТ Binding material.
Option A is incorrect because binding material is typically applied after wet rolling or alongside it to create the final seal.
Option B and C fail to establish the initial mechanical interlock via dry rolling before introducing fines.
D is correct тАФ The correct sequence in WBM construction is dry rolling to interlock aggregates, followed by filling voids with screenings, wet rolling to create a slurry, and final application of binding material.
In highway engineering, remember that 'Dry Rolling' always precedes 'Wet Rolling' to prevent shifting of aggregates; if you wet-roll first, the aggregate particles lose friction and slide.