Examoogle
ExamsTest SeriesRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
🛒0
अA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
© 2026 Examoogle. India's #1 competitive exam AI tutor.
🔒 SSL Secured📱 UPI Accepted🧾 GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
Subtotal₹0
Total₹0
Examoogle • User • info@examoogle.com • EE-2024-8821
Chapter 1 of 12 • Page 1 of 248🔒 Protected PDF • Watermarked
Back to Practice Questions
ElectricalPower System
PrevNext

How many days are required for 220 kv transformer for drying out.

A

10

B

25

C

35

D

45

Correct Answer

Concept & PrincipleElectricalPower System
Option A

10

Quick Summary: Drying out of a 220 kV transformer is a critical process performed before commissioning to ensure the moisture content in the cellulose insulation is reduced to safe limits. For large power transformers of this voltage class, a duration of approximately 10 days is typically required when using advanced techniques like hot oil circulation or vacuum drying.

💡 Explanation

Drying out of a 220 kV transformer is a critical process performed before commissioning to ensure the moisture content in the cellulose insulation is reduced to safe limits. For large power transformers of this voltage class, a duration of approximately 10 days is typically required when using advanced techniques like hot oil circulation or vacuum drying.

🔢 Key Formulas

Ploss∝I2RP_{loss} \propto I^2RPloss​∝I2R — used to calculate heat dissipation during short-circuit drying methods

m=V⋅ρ⋅(ω1−ω2)m = V \cdot \rho \cdot (\omega_1 - \omega_2)m=V⋅ρ⋅(ω1​−ω2​) — moisture mass removal calculation based on oil volume and humidity change

⚙️ Working Principle

The drying process removes moisture trapped in the solid insulation (paper) by applying heat and vacuum. By circulating hot transformer oil through a filter machine (or using vacuum heat cycles), the moisture migrates from the cellulose insulation into the oil or the vacuum space, where it is subsequently extracted.

📌 Key Points
  • ▸

    Drying is essential to prevent dielectric breakdown due to high moisture in cellulose insulation.

  • ▸

    The 10-day duration is a standard estimation for 220 kV transformers using high-vacuum oil purification systems.

  • ▸

    Insulation resistance (IR) and Polarization Index (PI) are monitored throughout the process to verify moisture reduction.

✅ Advantages
  • ▸

    Increases the dielectric strength of the insulation system.

  • ▸

    Ensures long-term operational reliability of the transformer.

❌ Disadvantages / Limitations
  • ▸

    Extremely time-consuming process.

  • ▸

    Requires high-cost specialized equipment like vacuum-oil purifiers.

🛠️ Applications / Uses
  • ▸

    Pre-commissioning of new power transformers.

  • ▸

    Post-repair maintenance to remove ingress moisture.

📄 Additional Information
  • ▸

    The actual duration can vary depending on the initial moisture content and site environmental conditions.

  • ▸

    Option B, C, and D are incorrect as they represent significantly longer durations that would lead to unnecessary downtime and cost.

📊 Diagram / Illustration
Transformer Drying ProcessHeat SourceVacuum Pump
✅

A is correct — 10 days is the standard time required for drying out a 220 kV transformer before its final commissioning.

Core Concepts Used
Click any tag to open in AI Tutor
Transformer Insulation Moisture Ingress Vacuum Drying
💡 EXAM TIP

Always check the Polarization Index (PI) values after drying; if PI remains below 1.5, further drying is mandatory regardless of the time elapsed.

Related Questions

ElectricalPower System
The specified quantities of Generation bus is
ElectricalPower System
When an alternator connected to the bus-bar is shut down the bus-bar voltage will
ElectricalPower System
The current drawn by the line due to corona losses is _______
ElectricalPower System
The specified quantities of load bus are
ElectricalPower System
The advantages of high transmission voltage are ______

Discussion (0)

Loading discussion...
PrevNext