If 12 men or 18 boys can complete a task in 24 days, in how many days can 8 men and 6 boys complete the same task?
20 ┬аdays
24 ┬аdays
18 ┬аdays
22 ┬аdays
24 ┬аdays
Convert all workers into a single unit (either men or boys) using the given equivalence ratio before combining.
12 men or 18 boys can complete a task in 24 days. Find the days required for 8 men and 6 boys.
Days=Total┬аEfficiencyTotal┬аWorkтАЛ
Convert all workers into a single unit (either men or boys) using the given equivalence ratio before combining.
Adding the number of men and boys arithmetically without accounting for their different work efficiencies.
Establish Worker Equivalence
Equate the work done by 12 men to 18 boys to find the efficiency relation: 12M=18B.
12M=18BтЯ╣1M=23тАЛB
Convert Men to Equivalent Boys
Convert 8 men into equivalent boys using the ratio: 8M=8├Ч23тАЛB=12B.
8M=12B
Calculate Total Combined Workforce
Add the converted men's equivalent to the 6 boys: 12B+6B=18B.
12B+6B=18B
Determine Completion Time
Since 18 boys take 24 days to complete the task, 18 equivalent boys will also complete it in 24 days.
24┬аdays
B is correct because 8 men and 6 boys are equivalent to 18 boys, who complete the task in 24 days.
This equivalence method is essential for solving mixed-group problems in pipe-and-cistern and wages chapters.