If 330 persons can complete the construction of a shopping complex in 50 days, how many persons are required to complete the same work in 30 days?
550
450
198
505
550
Practice and solve "If 330 persons can complete the construction of a shopping complex in 50 days, how many persons are ..." for Mathematics - Previous Year Paper 2024. The correct answer is Option A: 550. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.