Mass curve can be plotted from
Load duration curve
Chronological load curve
Energy load curve
Both (a) and (b)
Chronological load curve
A mass curve (also known as a flow-duration curve or cumulative load curve) is derived by integrating the chronological load curve over a specific time interval. It represents the cumulative energy generated or consumed up to a certain time t, facilitating the determination of reservoir storage capacity in hydroelectric plants.
A mass curve (also known as a flow-duration curve or cumulative load curve) is derived by integrating the chronological load curve over a specific time interval. It represents the cumulative energy generated or consumed up to a certain time t, facilitating the determination of reservoir storage capacity in hydroelectric plants.
E(t)=тИл0tтАЛP(t)dt тАФ Cumulative energy representing the mass curve ordinate
PavgтАЛ=T1тАЛтИл0TтАЛP(t)dt тАФ Average load over time T
The chronological load curve plots instantaneous load against time. By integrating this curve, we obtain the total energy (area under the curve). The mass curve plots this cumulative energy (EcumтАЛ=тИл0tтАЛP(t)dt) against time, showing the total supply required over a duration.
The mass curve is essential for determining the storage capacity required for a hydro power plant.
It helps identify the critical dry period when inflow is less than the required demand.
The slope of the mass curve at any point represents the instantaneous load demand.
It is strictly dependent on the order of load occurrence, hence only derived from chronological data.
Allows calculation of reservoir storage requirements.
Helps in scheduling base load and peak load plants.
Does not show peak demand values as clearly as a load duration curve.
Calculation requires integration of chronological data.
Hydroelectric reservoir design.
Water resource management.
Long-term energy planning.
Load duration curve (Option A) is a rearrangement of chronological load data in descending order of magnitude, which loses the time sequence necessary for mass curve generation.
Energy load curve (Option C) represents cumulative energy but often lacks the precise temporal resolution required for reservoir management compared to the mass curve.
B is correct тАФ The mass curve is the integral of the chronological load curve, as it requires the exact time sequence to calculate cumulative energy storage requirements.
Always remember: Chronological load curves preserve time sequence (required for storage calculations), while load duration curves (LDC) discard time sequence to highlight magnitude distribution (used for plant selection).