Rishi can do a piece of work in 11 days. Shan is 10% more efficient than Rishi. The number of days taken by Shan to do the same piece of work is: 2969
10
20
11
15
10
Practice and solve "Rishi can do a piece of work in 11 days. Shan is 10% more efficient than Rishi. The number of days t..." for Mathematics - Previous Year Paper 2024. The correct answer is Option A: 10. Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.