Join 60,000+ competitive exam aspirants
The insulation level of 400 kV EHV overhead transmission line is decided on the basis of
Lightning over voltage
Switching over voltage
Corona inception voltage
Radio and TV interference
Switching over voltage
For transmission lines operating at 400 kV and above, the insulation level is primarily governed by switching over-voltages rather than lightning strikes. This is because, at higher voltages, the ratio of switching surge magnitude to the normal operating voltage becomes a critical factor in determining the air gap clearance and tower dimensions.
For transmission lines operating at 400 kV and above, the insulation level is primarily governed by switching over-voltages rather than lightning strikes. This is because, at higher voltages, the ratio of switching surge magnitude to the normal operating voltage becomes a critical factor in determining the air gap clearance and tower dimensions.
Vsw=k⋅Vph — Switching surge voltage where k is the switching surge factor
Vins≥BSL — Insulation level must be greater than Basic Switching Insulation Level
Switching surges occur due to circuit breaker operations, reclosing, or fault clearing, which generate transient waves that persist longer than lightning surges. As voltage levels increase, the dielectric strength of long air gaps under lightning impulses increases, but the strength under switching impulses remains relatively low, making it the limiting factor for insulation design.
Below 300 kV, lightning over-voltage is the primary concern for insulation coordination.
Switching surges are caused by system disturbances like line energization or faults.
Increasing the voltage level makes the air-gap insulation design more sensitive to slow-front switching surges.
Modern 400 kV and 765 kV systems use pre-insertion resistors in circuit breakers to reduce switching surge magnitudes.
Reduces the risk of insulation failure during standard system switching operations.
Allows for optimized tower window design and clearances.
Necessitates costlier, high-performance circuit breakers with pre-insertion resistors.
Increases the physical size requirements for tower structures to maintain safe air gaps.
Design of EHV (Extra High Voltage) transmission towers.
Selection of lightning arresters and transformer insulation levels.
Lightning surges are fast-front transients, whereas switching surges are slow-front transients.
Corona inception voltage is a criterion for conductor selection (bundle conductors) to minimize losses, not a criterion for insulation coordination.
Radio and TV interference (RIV) is a design parameter for conductor surface gradient, not for bulk insulation insulation level.
B is correct — Switching over-voltage is the governing factor for the insulation design of 400 kV and higher voltage transmission lines.
Always remember the 'break-point': Lightning surges dominate for voltages < 300 kV, while Switching surges dominate for voltages ≥ 300-400 kV.