Join 60,000+ competitive exam aspirants
If₁₂ men can finish a project in 10 days, how many men are needed to finish the same project in 8 days?
15
18
12
20
15
Practice and solve "If₁₂ men can finish a project in 10 days, how many men are needed to finish the same project in 8 d..." for RRB JE CBT-1 - Time and Work · The correct answer is Option A: 15 · Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.
Practice and solve "If₁₂ men can finish a project in 10 days, how many men are needed to finish the same project in 8 d..." for RRB JE CBT-1 - Time and Work · The correct answer is Option A: 15 · Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.