In order to have lower cost of electrical energy generation
The load factor and diversity factor should be low
The load factor should be low but diversity factor should be high
The load factor should be high but diversity factor low
The load factor and diversity factors should be high
The load factor and diversity factors should be high
To minimize the overall cost of electrical energy generation, both the load factor and the diversity factor should be as high as possible. A high load factor indicates efficient utilization of the generating equipment, while a high diversity factor minimizes the required maximum capacity of the power plant.
To minimize the overall cost of electrical energy generation, both the load factor and the diversity factor should be as high as possible. A high load factor indicates efficient utilization of the generating equipment, while a high diversity factor minimizes the required maximum capacity of the power plant.
Load┬аFactor=MaximumDemandAverageLoadтАЛ
Diversity┬аFactor=StationMaximumDemandтИСIndividualMaximumDemandsтАЛ
CostperunitтИЭLoadFactor1тАЛ
The cost per unit of energy is inversely proportional to the load factor because fixed costs are spread over a larger number of energy units. A high diversity factor signifies that the individual maximum demands of various consumers do not occur at the same time, thereby reducing the total installed capacity (MaxDemandTotalтАЛ<тИСIndividual┬аMax┬аDemands) required for the generating station.
Load factor measures the utilization of the plant capacity over a given period.
Diversity factor represents the non-coincidence of peak loads among different consumers.
Higher diversity factor leads to a smaller required station capacity.
High load factor ensures the capital investment is utilized effectively.
Lower fixed charges per unit of energy
Reduced requirement for standby capacity
Improved overall system stability
Difficult to maintain high load factor without industrial load management
Increased dependency on coordinated grid operations
Utility power system planning
Tariff structure design for industrial consumers
The diversity factor is always greater than 1 in practice for residential loads.
Option B and C are incorrect because a low load factor results in idle capacity, significantly increasing the cost per unit of energy produced.
D is correct тАФ Both factors should be high to ensure optimal utilization of capital assets and minimized total installed capacity requirements.
Remember that Diversity Factor is always тЙе1 and a higher value is better because it reduces the plant's capacity requirement; Load Factor is always тЙд1 and closer to 1 is better.