Examoogle
ExamsTest SeriesRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
🛒0
अA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
© 2026 Examoogle. India's #1 competitive exam AI tutor.
🔒 SSL Secured📱 UPI Accepted🧾 GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
Subtotal₹0
Total₹0
Examoogle • User • info@examoogle.com • EE-2024-8821
Chapter 1 of 12 • Page 1 of 248🔒 Protected PDF • Watermarked
Back to Practice Questions
ElectricalPower Generation
PrevNext

Which of the following generation needs permission from central electricity authority as per Electricity Act-2003?

A

Nuclear power

B

Thermal

C

Hydro

D

Solar

Correct Answer

Concept & PrincipleElectricalPower Generation
Option C

Hydro

Quick Summary: As per Section 8 of the Electricity Act 2003, any hydro-electric generation scheme requires the concurrence of the Central Electricity Authority (CEA) to ensure the project meets the guidelines related to river water utilization, safety, and technical stability. Unlike thermal or other power plants, which are governed largely by environmental and technical clearances, hydro projects involve complex civil engineering and water management aspects that necessitate centralized oversight.

💡 Explanation

As per Section 8 of the Electricity Act 2003, any hydro-electric generation scheme requires the concurrence of the Central Electricity Authority (CEA) to ensure the project meets the guidelines related to river water utilization, safety, and technical stability. Unlike thermal or other power plants, which are governed largely by environmental and technical clearances, hydro projects involve complex civil engineering and water management aspects that necessitate centralized oversight.

🔢 Key Formulas

P=ηρgQHP = \eta \rho g Q HP=ηρgQH — Theoretical power output of a hydro plant where QQQ is discharge and HHH is head.

⚙️ Working Principle

The CEA evaluates the Detailed Project Report (DPR) submitted by the developers. The assessment focuses on the optimal utilization of water resources, technical feasibility, the design of the dam and spillways, and the impact on the national/regional power grid. Once the technical viability and safety standards are validated, the CEA grants formal concurrence.

📌 Key Points
  • ▸

    Section 8 of the Electricity Act 2003 makes CEA concurrence mandatory for hydro schemes.

  • ▸

    The primary objective is to optimize the utilization of water resources in the national interest.

  • ▸

    Thermal, Nuclear, and Solar projects do not require similar statutory 'concurrence' under Section 8, though they require other environmental and regulatory clearances.

  • ▸

    CEA concurrence ensures safety and technical standard compliance for large dams and civil structures.

✅ Advantages
  • ▸

    Ensures technical safety of large-scale civil structures.

  • ▸

    Prevents sub-optimal utilization of national water resources.

  • ▸

    Standardization of design parameters for grid stability.

❌ Disadvantages / Limitations
  • ▸

    Extends the duration of the project approval process.

  • ▸

    Requires significant administrative coordination.

🛠️ Applications / Uses
  • ▸

    Large-scale Hydro-Electric Projects

  • ▸

    Pumped Storage Schemes

📄 Additional Information
  • ▸

    The Central Electricity Authority (CEA) acts as the principal technical advisor to the Ministry of Power.

  • ▸

    Only hydro projects above a certain capacity threshold typically undergo this exhaustive scrutiny process.

📊 Diagram / Illustration
CEA Concurrence RequirementHydro Project DPR SubmissionCEA Technical Concurrence
✅

C is correct — Hydro-electric projects require mandatory concurrence from the Central Electricity Authority (CEA) under Section 8 of the Electricity Act, 2003.

Core Concepts Used
Click any tag to open in AI Tutor
Electricity Act 2003 CEA Concurrence Hydro-Electric Generation Regulatory Compliance
💡 EXAM TIP

Always distinguish between 'environmental clearance' (which applies to almost all projects) and 'technical concurrence' (which is specific to hydro projects under the Electricity Act).

Related Questions

ElectricalPower Generation
For rural and remote areas, _________________for generation and distribution is permitted
ElectricalPower Generation
With reference to EC Act-2003,Setting up State Electricity Regulatory Commission (SERC) has been made_________
ElectricalPower Generation
The captive generation is ________as per Electricity Act-2003
ElectricalPower Generation
As per Electricity Act-2003, The generation of electricity is
ElectricalPower Generation
Which government body is working for standardization of products?

Discussion (0)

Loading discussion...
PrevNext