As per IRC specifications, the maximum spacing of contraction joints in reinforced cement concrete slab of thickness 20 cm is ___________.
40 m
10 m
14 m
4.5 m
14 m
According to IRC:58-2015, the maximum spacing of contraction joints in a reinforced cement concrete (RCC) pavement is limited to 14 meters. This limitation is placed to control the shrinkage and temperature-induced stresses, preventing uncontrolled random cracking of the slab.
IRC:58-2015 Guidelines for the Design of Plain Jointed Rigid Pavements for Highways
According to IRC:58-2015, the maximum spacing of contraction joints in a reinforced cement concrete (RCC) pavement is limited to 14 meters. This limitation is placed to control the shrinkage and temperature-induced stresses, preventing uncontrolled random cracking of the slab.
LcтАЛтЙд╬╝├Ч╬│cтАЛ2├Ч╧ГtтАЛтАЛ тАФ Where LcтАЛ is the slab length, ╧ГtтАЛ is the allowable tensile stress, ╬╝ is the coefficient of subgrade friction, and ╬│cтАЛ is the unit weight of concrete.
Concrete experiences volumetric changes due to moisture loss (shrinkage) and temperature fluctuations. If the slab length exceeds the tensile capacity of the concrete relative to the subgrade friction, cracks develop. Contraction joints provide a planned weakened plane where the slab can crack in a controlled manner, allowing for load transfer via reinforcement.
Contraction joints are essential to accommodate shrinkage during the hardening of concrete.
For unreinforced concrete pavements, the spacing is typically much shorter (4.5 m) to prevent mid-slab cracking.
In reinforced concrete, steel reinforcement allows for longer spacing by keeping cracks tightly closed.
Prevention of uncontrolled, irregular pavement cracking.
Improved service life and lower maintenance requirements.
Easier repair and sealing of joints compared to random cracks.
High initial cost of joint installation and sealing.
Potential for faulting if load transfer devices are not properly aligned.
Highway rigid pavements.
Airport runways and taxiways.
Industrial floor slabs with heavy traffic.
Option D (4.5 m) represents the standard spacing for plain cement concrete (PCC) pavements, not reinforced ones.
The spacing is dependent on the slab thickness and the amount of longitudinal reinforcement provided.
C is correct тАФ As per IRC specifications, the maximum spacing for contraction joints in an RCC slab is 14 m.
Always distinguish between PCC and RCC joint spacing; PCC (4.5 m) is governed by modulus of rupture, while RCC (up to 14 m) is governed by the steel-concrete bond and crack width control.