If₁₂ workers can complete a project in 20 days, how many workers are needed to complete the same project in 15 days?
15
16
18
20
16
Practice and solve "If₁₂ workers can complete a project in 20 days, how many workers are needed to complete the same pr..." for RRB JE CBT-1 - Time and Work · The correct answer is Option B: 16 · Detailed step-by-step solution, conceptual clarity, and formulas on Examoogle.