Examoogle
ExamsTest SeriesCBATRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
ЁЯЫТ0
рдЕA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
┬й 2026 Examoogle. India's #1 competitive exam AI tutor.
ЁЯФТ SSL SecuredЁЯУ▒ UPI AcceptedЁЯз╛ GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
SubtotalтВ╣0
TotalтВ╣0
Examoogle тАв User тАв info@examoogle.com тАв EE-2024-8821
Chapter 1 of 12 тАв Page 1 of 248ЁЯФТ Protected PDF тАв Watermarked
Back to Practice Questions
ElectricalPower Generation
PrevNext

Load frequency and economic dispatch controller are working

A

Independently

B

Together with

C

Sequential

D

None of above

Correct Answer

тЪЩя╕П TE тАв Technical Concept & PrincipleElectricalPower Generation
Option A

Independently

Quick Summary:

Load frequency control (LFC) and Economic Dispatch (ED) controllers operate independently because they function on different time scales and serve distinct objectives in power system operations. LFC is a high-speed control mechanism designed to maintain system frequency and power balance, whereas ED is a slower optimization process focused on minimizing the total fuel cost of power generation.

тЪЩя╕ПTETechnical SolutionConcept & Principle
ЁЯТб Explanation

Load frequency control (LFC) and Economic Dispatch (ED) controllers operate independently because they function on different time scales and serve distinct objectives in power system operations. LFC is a high-speed control mechanism designed to maintain system frequency and power balance, whereas ED is a slower optimization process focused on minimizing the total fuel cost of power generation.

ЁЯФв Key Formulas

╬ФP=B╬Фf\Delta P = B \Delta f╬ФP=B╬Фf тАФ Relation between power change and frequency deviation in LFC

dCidPi=╬╗\frac{dC_i}{dP_i} = \lambdadPiтАЛdCiтАЛтАЛ=╬╗ тАФ Incremental cost equality for Economic Dispatch

тЪЩя╕П Working Principle

The LFC operates in the secondary control loop to adjust the reference power set points of generators to mitigate frequency deviations occurring within seconds. In contrast, the ED controller performs iterative optimization over intervals of minutes (or even hours) to assign optimal generation levels to units based on their incremental cost curves, ensuring the system operates at the lowest possible cost while respecting generator constraints.

ЁЯУМ Key Points
  • тЦ╕

    LFC is part of the Automatic Generation Control (AGC) which acts in the short term.

  • тЦ╕

    Economic Dispatch is part of the tertiary control level which acts in the medium term.

  • тЦ╕

    The separation of time scales allows these systems to work independently without interference.

  • тЦ╕

    Interaction between these systems occurs only at the generator control set-point level.

тЬЕ Advantages
  • тЦ╕

    Improved stability of system frequency

  • тЦ╕

    Optimization of fuel usage for interconnected power systems

тЭМ Disadvantages / Limitations
  • тЦ╕

    Higher complexity in multi-area coordination

  • тЦ╕

    Potential for conflict if time scales overlap significantly

ЁЯЫая╕П Applications / Uses
  • тЦ╕

    Grid frequency regulation

  • тЦ╕

    Inter-area power interchange scheduling

ЁЯУД Additional Information
  • тЦ╕

    LFC is essentially a closed-loop control system (Primary/Secondary).

  • тЦ╕

    ED is essentially an open-loop optimization process (Tertiary).

ЁЯУК Diagram / Illustration
Power System Control Hierarchy Load FrequencyControl (Time: Seconds) Economic Dispatch (Time: Minutes) Frequency Regulation Cost Optimization
тЬЕ

A is correct тАФ The Load Frequency Controller and Economic Dispatch Controller function independently due to the significant difference in their response time constants and operational objectives.

Core Concepts Used
Click any tag to open in AI Tutor
Automatic Generation Control (AGC) Incremental Cost Curve Primary vs Secondary Control
ЁЯТб EXAM TIP

Always remember the hierarchy: Primary (Governor/Fast) тЖТ Secondary (LFC/Minutes) тЖТ Tertiary (Economic Dispatch/Extended time).

Related Questions

ElectricalPower Generation
For rural and remote areas, _________________for generation and distribution is permitted
ElectricalPower Generation
With reference to EC Act-2003,Setting up State Electricity Regulatory Commission (SERC) has been made_________
ElectricalPower Generation
Which of the following generation needs permission from central electricity authority as per Electricity Act-2003?
ElectricalPower Generation
The captive generation is ________as per Electricity Act-2003
ElectricalPower Generation
As per Electricity Act-2003, The generation of electricity is

Discussion (0)

Loading discussion...
PrevNext