Examoogle
ExamsTest SeriesCBATRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
ЁЯЫТ0
рдЕA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
┬й 2026 Examoogle. India's #1 competitive exam AI tutor.
ЁЯФТ SSL SecuredЁЯУ▒ UPI AcceptedЁЯз╛ GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
SubtotalтВ╣0
TotalтВ╣0
Examoogle тАв User тАв info@examoogle.com тАв EE-2024-8821
Chapter 1 of 12 тАв Page 1 of 248ЁЯФТ Protected PDF тАв Watermarked
Back to Practice Questions
ElectricalPower Generation
PrevNext

The installation time for a gas turbine power plant is

A

Comparatively less than thermal power plant

B

Comparatively more than thermal power plant

C

Equal to thermal power plant

D

Very much longer than thermal power plant

Correct Answer

тЪЩя╕П TE тАв Technical Concept & PrincipleElectricalPower Generation
Option A

Comparatively less than thermal power plant

Quick Summary:

Gas turbine power plants require significantly less installation time compared to thermal (coal-fired) power plants because they consist of compact, modular components. Thermal power plants require large-scale civil works, massive steam generators, and complex boiler setups that lead to much longer construction and commissioning periods.

тЪЩя╕ПTETechnical SolutionConcept & Principle
ЁЯТб Explanation

Gas turbine power plants require significantly less installation time compared to thermal (coal-fired) power plants because they consist of compact, modular components. Thermal power plants require large-scale civil works, massive steam generators, and complex boiler setups that lead to much longer construction and commissioning periods.

ЁЯФв Key Formulas

Wnet=WturbineтИТWcompressorW_{net} = W_{turbine} - W_{compressor}WnetтАЛ=WturbineтАЛтИТWcompressorтАЛ тАФ Net work output of a gas turbine

╬╖th=1тИТ1(rp)╬│тИТ1╬│\eta_{th} = 1 - \frac{1}{(r_p)^{\frac{\gamma-1}{\gamma}}}╬╖thтАЛ=1тИТ(rpтАЛ)╬│╬│тИТ1тАЛ1тАЛ тАФ Thermal efficiency based on pressure ratio

тЪЩя╕П Working Principle

The principle relies on the Brayton Cycle where air is compressed, heated, and expanded through a turbine. Because there is no need for large steam boilers, cooling towers, or extensive coal handling units, the site preparation and installation are modular and rapid.

ЁЯУМ Key Points
  • тЦ╕

    Gas turbine plants are ideal for peak load duty.

  • тЦ╕

    Thermal plants are typically used for base load duty due to their large size and slow startup.

  • тЦ╕

    Civil engineering requirements for gas turbines are minimal compared to the elaborate foundations required for heavy thermal power equipment.

тЬЕ Advantages
  • тЦ╕

    Lower capital investment

  • тЦ╕

    Quick start-up and shutdown time

  • тЦ╕

    Low maintenance cost

  • тЦ╕

    Small floor area required

тЭМ Disadvantages / Limitations
  • тЦ╕

    Lower overall thermal efficiency

  • тЦ╕

    High running cost due to expensive fuel (natural gas/distillate oil)

  • тЦ╕

    Short life span of turbine blades due to high operating temperatures

ЁЯЫая╕П Applications / Uses
  • тЦ╕

    Peak load power generation

  • тЦ╕

    Standby power units

  • тЦ╕

    Industrial captive power plants

ЁЯФД Comparison Table
FeatureGas TurbineThermal Plant

Installation Time

Very Short (Months)

Very Long (Years)

ЁЯУД Additional Information
  • тЦ╕

    Thermal power plants involve complex logistics including coal transport networks and water supply systems.

  • тЦ╕

    Option B, C, and D are incorrect because they ignore the compact and modular nature of gas turbine systems compared to the massive scale of steam-based thermal plants.

ЁЯУК Diagram / Illustration
Installation Time ComparisonGas Turbine TimeThermal Plant TimeT_gas <T_thermal
тЬЕ

A is correct тАФ The modular design of gas turbine plants allows for much faster installation and commissioning than large-scale coal-fired thermal power plants.

Core Concepts Used
Click any tag to open in AI Tutor
Power Generation Economics Plant Load Factor Brayton Cycle Project Management in Energy
ЁЯТб EXAM TIP

Always relate plant installation time to the complexity of the heat source; coal-fired thermal plants are complex because they require extensive boilers and steam-cycle infrastructure.

Related Questions

ElectricalPower Generation
For rural and remote areas, _________________for generation and distribution is permitted
ElectricalPower Generation
With reference to EC Act-2003,Setting up State Electricity Regulatory Commission (SERC) has been made_________
ElectricalPower Generation
Which of the following generation needs permission from central electricity authority as per Electricity Act-2003?
ElectricalPower Generation
The captive generation is ________as per Electricity Act-2003
ElectricalPower Generation
As per Electricity Act-2003, The generation of electricity is