Examoogle
ExamsTest SeriesCBATRank CheckPrevious Year PapersPassBook StoreMy BooksAI Tutor
🛒0
अA
Examoogle

India's most trusted platform for competitive exam PDF books. Expert-authored, watermark-protected, instant access.

Exams & Practice
All Exams & SyllabusMock Test SeriesPrevious Year PapersPractice Questions (MCQs)Recruitment Notifications
Quick Links
Examoogle AI TutorExam NewsBook StoreMy BooksLogin / Sign Up
Support
About UsRefund PolicyPrivacy PolicyTerms of UseContact Us
© 2026 Examoogle. India's #1 competitive exam AI tutor.
🔒 SSL Secured📱 UPI Accepted🧾 GST Invoice
Examoogle

Join 60,000+ competitive exam aspirants

or with email
By continuing, you agree to ourTerms of Service&Privacy Policy
Your Cart
Subtotal₹0
Total₹0
Examoogle • User • info@examoogle.com • EE-2024-8821
Chapter 1 of 12 • Page 1 of 248🔒 Protected PDF • Watermarked
Back to Practice Questions
ElectricalPower Generation
PrevNext

The load factor is

A

Always less than unity

B

Less than or greater than 1

C

Always greater than 1

D

Less than zero

Correct Answer

⚙️ TE • Technical Concept & PrincipleElectricalPower Generation
Option A

Always less than unity

Quick Summary:

The load factor is the ratio of average load to the maximum demand during a given period. Since the average load cannot exceed the maximum demand, the ratio is always less than unity (1).

⚙️TETechnical SolutionConcept & Principle
💡 Explanation

The load factor is the ratio of average load to the maximum demand during a given period. Since the average load cannot exceed the maximum demand, the ratio is always less than unity (1).

🔢 Key Formulas

Load Factor=Average LoadMaximum Demand\text{Load Factor} = \frac{\text{Average Load}}{\text{Maximum Demand}}Load Factor=Maximum DemandAverage Load​

Load Factor=Energy Consumed in Time TMaximum Demand×T\text{Load Factor} = \frac{\text{Energy Consumed in Time T}}{\text{Maximum Demand} \times T}Load Factor=Maximum Demand×TEnergy Consumed in Time T​

⚙️ Working Principle

In a power system, the maximum demand refers to the peak power required during a specific period, while the average load is the total energy consumed divided by time. Because the average load accounts for periods of low demand, it is mathematically constrained to be less than or equal to the peak demand. Thus, the ratio Average LoadMaximum Demand\frac{\text{Average Load}}{\text{Maximum Demand}}Maximum DemandAverage Load​ never exceeds 1 in a practical power system.

📌 Key Points
  • ▸

    A higher load factor indicates more efficient utilization of generating equipment.

  • ▸

    The maximum possible value of the load factor is 1, which occurs if the load remains constant throughout the period.

  • ▸

    It is a dimensionless quantity used to assess the efficiency of power plants.

✅ Advantages
  • ▸

    Indicates better utilization of plant capacity

  • ▸

    Helps in reducing the overall cost of electricity generation

❌ Disadvantages / Limitations
  • ▸

    Low load factor results in high fixed costs per unit of electricity generated

🛠️ Applications / Uses
  • ▸

    Used by utility companies for tariff structuring

  • ▸

    Used in planning and sizing of power plant equipment

📄 Additional Information
  • ▸

    The load factor is always between 0 and 1.

  • ▸

    Option B, C, and D are incorrect because the average load is fundamentally limited by the installed maximum demand, making values >1> 1>1 or <0< 0<0 physically impossible in standard power generation.

✅

A is correct — The load factor is defined as the ratio of average load to maximum demand, which cannot exceed unity in any practical electrical system.

Core Concepts Used
Click any tag to open in AI Tutor
Load Curve Maximum Demand Average Load Plant Efficiency
💡 EXAM TIP

Always remember: Load factor ≤1\leq 1≤1 and Diversity factor ≥1\geq 1≥1; these are key metrics in power system economics.

Related Questions

ElectricalPower Generation
For rural and remote areas, _________________for generation and distribution is permitted
ElectricalPower Generation
With reference to EC Act-2003,Setting up State Electricity Regulatory Commission (SERC) has been made_________
ElectricalPower Generation
Which of the following generation needs permission from central electricity authority as per Electricity Act-2003?
ElectricalPower Generation
The captive generation is ________as per Electricity Act-2003
ElectricalPower Generation
As per Electricity Act-2003, The generation of electricity is

Discussion (0)

Loading discussion...
PrevNext